Project 9153 - Vitamin Shoppe, 123 Weber Road, Bolingbrook, Illinois 60440

This page was last updated on 03/24/2015

Payment Requests & Change Orders


Requests To Ownership For Direct Payment Of Services Rendered:

To be eligible for payment for services rendered for this project a signed subcontract, completed W-9 and certificate of insurance must be on file in FJDC's office.

All requests for payment for this project must include: 1) Invoice reflecting actual work performed in place less current contract 10% retention; 2) Completed and signed partial and/or respective final waiver of lien, signed and notarized with any respective backup material and/or sub-sub waivers.

All requests for payment for services rendered at the site shall be submitted by fax or email by no later than midnight on the following dates:

Complete requests submitted after the above referenced dates shall be held over and submitted on the next submittal date.

After approval of submitted request for payment, payment shall be made available by owner for pickup or delivery in approx. 10 days from date of submittal.

The payment of progress payments to the Subcontractor shall not be construed as an absolute acceptance of the work done up to the time of such payment but the entire work is to be subject to inspection and approval by the owner and/or architect at the time when the General Contract is completed.


Change Orders:

  1. Owner/Architect reserves the right to make changes or alterations in the work at any time prior to final completion.
  2. No payment shall be due for any additional or extra work without written consent of Owner/Architect. All requests for changes by subcontractor must be submitted in writing to contractor within 120 hours from the date subcontractor is made aware of any contract change.