BID SPREAD SHEET                
  Project: Vitamin Shoppe   Contractor: FJ Development Corp. of Illinois  
  Location: 123 N. Weber Road   Date:   02-02-15 02-23-15 Revised  
  Location: Bolingbrook, Illinois 60440 Design Type:   Per Drawings    
  Building SF:   3000     Site SF:   23407      
  Site #: 130072     # OCC:    83      
  # of Signage:    3     # of Parks:    25      
   
    Construction Description   Qty Units Unit Cost Total LL Total Tenant
II. SITE WORK  
   2.1 ON-SITE CONSTRUCTION  
  A. Demolition/Land Clearance         $14,300 $0
  Tree Removal 1 LS  $    1,500.00  $        1,500.00  $                  -    
  Demolition / Asphalt Removal 1 LS  $  12,800.00  $      12,800.00  $                  -    
~ Other                
  B. Site Clearing              $             -    $             -  
             $                  -    $                  -  
  C. Grading(Excavation,Backfill,Compaction)  $    7,360.75  $             -  
  Black Dirt Import     10 SEMI  $       350.00  $        3,500.00  $                  -    
  6' H Temporary Security Fence In Ground 755 LF  $          2.65  $        2,000.75  $                  -  
  Privacy Screening     755 LF  $          2.00  $        1,510.00  $                  -  
  24' Temporary Security Fence Gate 2 EA  $       175.00  $           350.00  $                  -  
  D. Site Construction  $  69,315.00  $             -  
~ Bituminous Concrete Paving, HC Signage, Stripping, Bumpers  1 LS  $  37,615.00  $      37,615.00  $                  -    
  Concrete curbs incl excavation 780 LS  $         22.44  $      17,500.00  $                  -    
  Sidewalk incl excavation 700 SF  $          6.00  $        4,200.00  $                  -    
  ADA Sidewalk pads 3 EA  $       250.00  $           750.00  $                  -    
  Light Pole Base incl excavation 1 EA  $       750.00  $           750.00  $                  -    
  Curb & Gutter Structures Layout 1 LS  $    3,900.00  $        3,900.00  $                  -    
  Building Layout 1 LS  $       950.00  $           950.00  $                  -    
  Trash Enclosure Gates 1 LS  $    3,650.00  $        3,650.00  $                  -    
  Masonry Trash enclosure 1 LS  $    3,395.00  $        3,395.00  $                  -    
  Monument Sign Masonry 1 LS  $    2,591.00  $        2,591.00  $                  -    
  Sign Foundation incl excavation 1 EA  $    1,500.00  $        1,500.00    
  Bollards - 6" concrete filled 4 EA  $       410.00  $        1,640.00  $                  -    
~ Other        $                  -    $                  -  
  E. Utilities $81,438.00 $0.00
~ 8" DIP Water Service 1 LS  $  31,650.00  $      31,650.00  $                  -    
  1" Water Service To Building 1 LS  $    2,500.00  $        2,500.00  $                  -    
  Sanitary Service 1 LS  $  17,000.00  $      17,000.00  $                  -    
  Storm Water Service 1 LS  $  27,000.00  $      27,000.00  $                  -    
~ Gas Service Sleeve w/Pull String 42 LF  $         12.00  $           504.00  $                  -  
~ 4" PVC Conduit for ComEd with Pull String 66 LS  $         12.00  $           792.00  $                  -  
  4" PVC Tele Conduit Sleeve w/Pull String  66 LS  $         12.00  $           792.00  $                  -  
  Transformer Concrete Base 1 LS  $    1,200.00  $        1,200.00  $                  -  
  F. Landscape & Irrigation  $  20,435.83  $             -  
  Landscaping     1 LS  $  11,810.83  $      11,810.83  $                  -    
~ Irrigation System     1 LS  $    8,625.00  $        8,625.00  $                  -    
  G. Additional site work not covered  $             -    $             -  
    Other 1    $              -    $                  -    
COMPLETE SITE SUB-TOTAL  $192,849.58  $             -  
Profit, GC Office Overhead, licensing and Insurance  $      19,284.96  $                  -  
On Site Supervision + Project Manager - on and off site  $        8,871.08  $                  -  
General Conditions (Dumpsters, Port-A-Let, Office & Storage Trailers, cleaning…etc.)  $        5,206.94  $                  -  
Bonds    
TOTAL ON-SITE CONSTRUCTION  $226,212.56  $             -  
Cost per SF  $              9.66  $                  -  
   
   
    Construction Description   Units   Unit Cost Total LL Total Tenant
III. BUILDING                  
  3. CONCRETE  $  42,850.00  $             -  
~ Building Foundation & Dumpster Foundation 1 LS  $  22,500.00  $      22,500.00  $                  -    
  Slab Floor Concrete & Dumpster Enclosure 2,827 LS  $          4.79  $      13,550.00  $                  -    
  Building Excavation     1 LS  $    6,800.00  $        6,800.00  $                  -    
  Other 0        
  4. MASONRY  $  67,952.50  $             -  
  Harvard Brick 12" Block 2,430 SF  $          9.50  $      23,085.00  $                  -    
  Harvard Brick 10" Block 2,475 SF  $          8.50  $      21,037.50  $                  -    
  Split Face Block 2,040 SF  $         10.73  $      21,880.00  $                  -    
  Pre-cast bottom band 65 LF  $         30.00  $        1,950.00  $                  -    
  5. METAL  $  38,000.00  $             -  
~ Structural Steel Package Installed 1 LS  $  38,000.00  $      38,000.00  $                  -    
  Other          
  6. ROUGH CARPENTRY/FINISH CARPENTRY  $  12,075.00  $    4,290.00
~ Supply and Install wood blocking for parapets and Roof Hatch curb. S&I Steel stud framing and 2 layers of Foam Insulation at exterior walls. 1 LS  $  12,075.00  $      12,075.00  $                  -  
  Supply and install 3-5/8" and 6" 20Ga. Steel studs at 24"OC as specified except at Mop sink (16"OC). Provide wood blocking as needed for Toilet accessories, Ladder, and Steel flat stock blocking for Display shelving units against walls. Frame for Roof Access headwalls. Frame platform deck for Water Heater and sheet with 5/8" plywood. Provide one sheet of 5/8" BC plywood for Electrical panels. 1 LS  $    4,290.00  $                  -    $        4,290.00
  Other 0      $                  -    
  7. THERMAL & MOISTURE PROTECTION  $  28,600.00  $             -  
~ Roofing & SM - Firestone TPO & Hatch 1 LS  $  27,400.00  $      27,400.00  $                  -    
  Caulking & Sealents     1 LS  $    1,200.00  $        1,200.00  $                  -    
~ Other 0      $                  -    $                  -  
  8. DOORS, WINDOWS & GLASS  $  29,075.00  $    4,540.21
~ HM Doors, Frames & Hardware 4 EA  $    1,331.30  $        1,650.00  $        3,675.21  
  Door Labor 1 LS  $    1,290.00  $           425.00  $           865.00  
~ Aluminum Framed Glazed Storefront 1 LS  $  27,000.00  $      27,000.00  $                  -    
  Other          
  9. FINISHES  $             -    $  64,582.16
~ Gypsum Board & Cement Board 1 LS  $    6,700.00  $                  -    $        6,700.00  
~ Floor & Wall:                
  CT-1 Porcelain Tile  2,552 SF  $          9.19  $                  -    $      23,451.50  
  VCT-1 Armstrong 51908 VCT 62 SF  $          2.00  $                  -    $           124.52  
  Walk off Mats from MBG, Inc. 2 LS  $       241.44  $                  -    $           482.88  
  CS-1 Armorseal Floor-Plex 7100 w/prep 467 SF  $          4.28  $                  -    $        2,000.00  
  VB-1 Roppe Base 360 LF  $          3.10  $                  -    $        1,116.00  
  VB-2 Johnsonite Base 240 LF  $          3.10  $                  -    $           744.00  
  CT-1 (Sundries) 1 LS  $    2,563.26  $                  -    $        2,563.26  
  VCT Adhesive / VB Adhesive 1 LS  $       250.00  $                  -    $           250.00  
  Ardex, Tile Floor Preparation 1 LS  $       750.00  $                  -    $           750.00  
  Material Shipping / Expediting / Handling 1 LS  $    2,500.00  $                  -    $        2,500.00  
~ Suspended Acoustical Panel Ceilings 1 LS  $    9,575.00  $                  -    $        9,575.00  
~ FRP -S&I FRP wainscot in washroom, Drinking Fountain, and at Mop Sink surround 1 LS  $    1,995.00  $                  -    $        9,575.00  
  Painting       1 LS  $    4,750.00    $        4,750.00  
  Other          
  10. SPECIALTIES  $      275.00  $    1,067.86
  Fire Extinguishers - 10# ABC 2 EA  $         77.93  $                  -    $           155.86  
  Miscellaneous - Labor only to install Toilet Accessories, Fire extinguishers (2), Interior room sign (1), and the Roof Access ladder. 1 EA  $       570.00  $                  -    $           570.00  
  Washroom Hardware & Signage 1 LS  $       342.00  $                  -    $           342.00  
  Knox Box 1 EA $275.00  $           275.00  
  11. EQUIPMENT  $             -    $             -  
  Other 0 LS  $              -    $                  -    NIC 
  12. FURNISHINGS  $             -    $             -  
  Shelving and Workstations Install (see Equipment installation above) 0 LS  $              -    $                  -    NIC 
  13. SPECIAL CONSTRUCTION (not applicable)  $             -    $             -  
  14. CONVEYING SYSTEM (not applicable)  $             -    $             -  
  15. MECHANICAL  $  15,000.00  $  29,316.61
~ Interior Rough & Trim Plumbing 1 LS  $  10,850.00  $                  -    $      10,850.00  
  Interior Plumbing Fixtures 1 LS  $    1,816.61  $                  -    $        1,816.61  
~ Stub and Backflow for Irigation 1 LS  $       850.00  $                  -    $           850.00  
  Wet Sprinkler Systems 0 LS    $                  -    NIC   
  HVAC including RTU's, Ductwork, Fans, Grills, Gas Piping, Thermostats 1 LS  $  30,800.00  $      15,000.00  $      15,800.00  
  16. ELECTRICAL  $  20,610.00  $  23,350.73
  Electrical  1 LS  $  32,800.00  $      16,300.00  $      16,500.00
  Lighting Fixtures from Specialty Lighting Group 1 LS  $    6,850.73  $                  -    $        6,850.73  
  Exterior Lighting Fixtures 1 LS  $    4,310.00  $        4,310.00  
  Telephone & Data (conduits only) 0 LS  $              -    INC   INC   
  Sound System from Trusonic, Inc. 0 LS  $              -    NIC   NIC   
~ Security & FA Systems 0 LS  $              -    NIC   NIC   
BUILDING COST SUB-TOTAL   $254,437.50  $127,147.57
Profit, GC Office Overhead, licensing and Insurance  $      25,443.75  $      12,714.76  $   57,443.46
On Site Supervision + Project Manager - on and off site  $      11,704.12  $        5,848.79  $   26,423.99
General Conditions (Dumpsters, Port-A-Let, Office & Storage Trailers, cleaning…etc.)  $        6,869.81  $        3,432.98  $   15,509.74
Bonds    
GC BUILDING GRAND TOTAL  $298,455.19  $149,144.10
Cost per SF  $             99.49  $             49.71
TOTAL BUILDING & SITE  $524,667.74  $149,144.10  $ 673,811.84
    690000
  17. ALTERNATES (ADD/DEDUCT)      $ (16,188.16)
1 Supply and install Firestone Walkway pad per Firestone detail UT-M-1 (cost per LF)  $            15.24  $                 -   97.65%
2    $                 -    $                 -  
   
WE DO NOT INCLUDE: Permit fees, dewatering, shoring, undercutting, removal of bad soils, removal of buried concrete, removal of buried debris, environmental testing or reporting, environmental remediation work, installation of temporary roads, premium time, moving or bracing of existing utility poles, asbestos removal, compaction testing, utility disconnect or reconnect fees, removal of A/C freon, dewatering using well points or pumps requiring operators.  
Respectfully Submitted By:  
FJ DEVELOPMENT CORP. of ILLINOIS  
  Signature
 
   
  No Addendums  
Signature: Date: Monday, February 23, 2015  
  John Friedberg, President     Revised